He FC Barcelona He has serious problems to fulfill his promise of a triumphal return to the new Camp We. After announcing that the stadium would open without a license from the City hallfinally the approval has arrived, but with small print. A green light in which the initial amount of capacity is expected to lower to the 27,000 viewersmuch lower than the 60,000 they promised in their day.
However, the happiness of the Culés still depends on what he lacks to be fulfilled before Catalan legislation. Jordi VallsBarcelona acting, confirmed that they still need even three licenses In order to have permission for the partial occupation of the stadium: «To obtain it, an ECA certificate of environmental control, the end of work and the district is required (from Les Corts). That means that inspections will have to be carried out, especially security And, when we have all that, a decision will be made, ”he explained in an appearance before the media.
According to sources from the Barcelona town hall, The first phase of the works has been divided into three subfases, where the construction of the first two stands of the three that make up the project would be included. The current objective is to finish the first subphase and open the enclosure for those 27,000 seats, located in the southern goal area and tribune. And get, in the following months, The corresponding first partial occupation license as the Barcelona City Council is certifying the completion of the different phases of the work.
Barcelona wants Camp Nou against Valencia
Phase 1 includes the southern goal and the gallery, with capacity for 27,000 spectators; Phase 1B incorporates the side, which will increase the capacity to 45,000, and phase 1C will add the north goal to complete the first 60,000 seats.
Phase 2 remains that of the third grader, whose construction is initially planned for a year and that will allow expanding the capacity of the stadium to a final capacity of almost 105,000 spectators.
This subdivision of the first phase will make Barça obtain the first partial occupation license progressively and thus release the stadium on September 14when you will receive Valencia On the fourth day of LaLiga.