He Barça He has a dilemma of the fat people for the next weeks with the dispute of his first Liga match at home against the Valenciagiven the delays and numerous deficiencies of the new Camp We that prevent partially returning to the stadium, leaving the stadium as the only way Johan Cruyff… that does not comply with the regulations of the employer to play in the First Division.
The European Clubs Association (ECA) has detected up to 200 deficiencies in the first phase of the works of the Camp We. These technical problems put at risk the celebration of the Fourth League Day match against Valencia, scheduled for mid -September at the new stadium, date that today seems difficult to meet. He Barça He had planned to play the first three days as a visitor due to the delay of the works, but he hoped to partially reopen his stadium in that duel. If incidents are not solved, Joan Laporta and the Barça had to resort to alternatives such as Johan Cruyff To house league matches.
He Barcelona City Council It has already granted a modified license to partially open the stadium with 27,000 locations, which would be extended progressively until reaching 60,000 seats at the end of the year. However, to achieve this, the club must present key certificates: the environmental control of the ECA, the completion of work and the permit of the district of Les Corts. All this requires security inspections that, for now, have not been overcome.
Con Montjuic occupied by a post Malone concert on September 12 at the Lluís Companys Stadium, the option of the Stadium Johan Cruyff It has appeared on the table. But its reduced capacity of 6,000 seats does not meet the minimum of 8,000 required by the Liga For First Division stages. In addition, it lacks VAR installation and presents infrastructure problems: insufficient restoration services, sinks in poor condition and a security system adapted to lower categories matches.
In economic terms, play their games in the Johan Cruyff until they can make the leap to Camp We It would also be a strong impact, since only 7% of the social mass of the club in the stadium fit, these would be the only ones that could access tickets, which would drastically reduce collection and habitual assistance.
The most advanced areas of the reform of the Camp Nou They are the tribune and the southern goal, where the first 27,000 locations available would be located. But despite this, there are still without ending key elements, such as the press zone, provisional media booths and the future area for the new culé animation tier. Municipal technicians and firefighters have expressed concern for the safety of accesses and the evacuation of spectators on different occasions during the last weeks.
The construction company Limak Work counterreloj to solve the deficiencies and obtain the necessary approval. While Laporta insists that Barça will receive the Valencia In the new Camp We On September 14, doubts grow within the City hall and in the fans itself. If permission is not achieved, Johan Cruyff It is presented as the last alternative, although insufficient for the demands of the competition and the expectations of the club. He Barça y Laporta They have a very fat mess with the premiere at home of the team of Which one Flick…