The main structure of La Romareda It will be demolished this summer and the South goal, An action that corresponds to the second phase of his works after the end of the season, after one year of the beginning of the actions on the pitch.

The summer period will be the most intensive phase of the year, in the words of those responsible for society NEW ROMAREDAwhich is currently disassembling the lover cover of the stadium and the standingerío closest to the field.

At present, the operators who participate in the works are sixty, although it is expected that, at its peak, they will reach three hundred.

The tasks belong to the second stage of the construction, executed with a budget of 124.5 million euros, and that continue with the deadlines stipulated in the beginning. The demolition of the structure will begin next week and, until October, the ground movements and relevant excavations will be happening.

“A very symbolic and complicated moment in this phase will be the demolition of the spotlight towers, because of the height they have and the difficulty they entail,” the mayor of Zaragoza, Natalia Chuecaon a visit on Tuesday to the stadium works.

The governor explained that the first phase has been fulfilled, in which the old southern goal was demolished and 24,000 square meters were removed, 5,000 tons of concrete and another 500 steel. Through the use of concrete, precisely, they have built the shoes and foundation slabs of the new sector, in which they have also used corrugated steel.

Read too

It was on June 16, finally, when the works began in the rest of the stadium, and the seats, lathes and spotlights were disassembled. The latter will serve to illuminate what will be the new white house in the next two seasons and that, as he clarified Chuecait will not have animation tier.

“This project is not only a football stadium, it is much more: we will be able to have great concerts and a new center for business and social meetings. Without a doubt, it will be a new epicenter of the city as soon as the work is completed,” said the mayor, who has not yet revealed technical details, such as the characteristics of the video stores, waiting for the pertinent tender to occur.